LUDHIANA: Delays in rehabilitation and removal of encroachments close to Jagraon bridge is additional delaying reconstruction work of the bridge right here. The municipal corporation of the town is but to arrange a plan to rehabilitate the encroachers, and till then neither encroachments can also be removed nor demolition of old a part of bridge can also be started.
Earlier there used to be a plan to dismantle the old portion of the bridge from this week, however now work will start only when the encroachments will be rehabilitation completely.
The civic frame after carrying out a survey of the area had sought record from the revenue division to test whether that land belongs to the municipal corporation (MC) or some other division. The revenue division has informed the MC that land belongs to MC, Railway and even National Highway Authority of India (NHAI). The MC has now determined to demolish the illegal buildings of its own however they will rope in officials from different two departments as smartly.
For the rehabilitation of the encroachers, the officials are making plans to shift them to residing devices in Giaspura. For this they require permissions from MC basic area, which is but to be formed. The officials claimed that they're going to have to wait for a minimum of 10-12 days for this.
The MC commissioner, Jaskiran Singh, stated that they were trying to rehabilitate the folks in order that there must be no hue and cry while demolition of the buildings.
“It will take a few days to meet the formalities,” he stated.
Notably, one facet of this bridge used to be closed by way of the railways in July 2016. It used to be declared that the construction used to be unsafe for movement of visitors. After almost three hundred and sixty five days, the state government launched funds for the project to MC, that have been additional transferred to the railways. The MC had paid Rs 24.30 crore to the railways within the month of July last yr however nonetheless the work may just now not kick off.
Earlier there used to be a plan to dismantle the old portion of the bridge from this week, however now work will start only when the encroachments will be rehabilitation completely.
The civic frame after carrying out a survey of the area had sought record from the revenue division to test whether that land belongs to the municipal corporation (MC) or some other division. The revenue division has informed the MC that land belongs to MC, Railway and even National Highway Authority of India (NHAI). The MC has now determined to demolish the illegal buildings of its own however they will rope in officials from different two departments as smartly.
For the rehabilitation of the encroachers, the officials are making plans to shift them to residing devices in Giaspura. For this they require permissions from MC basic area, which is but to be formed. The officials claimed that they're going to have to wait for a minimum of 10-12 days for this.
The MC commissioner, Jaskiran Singh, stated that they were trying to rehabilitate the folks in order that there must be no hue and cry while demolition of the buildings.
“It will take a few days to meet the formalities,” he stated.
Notably, one facet of this bridge used to be closed by way of the railways in July 2016. It used to be declared that the construction used to be unsafe for movement of visitors. After almost three hundred and sixty five days, the state government launched funds for the project to MC, that have been additional transferred to the railways. The MC had paid Rs 24.30 crore to the railways within the month of July last yr however nonetheless the work may just now not kick off.
Removal, rehabilitation of encroachers delaying Jagraon bridge reconstruction