Wall collapse: HC suggests inspection by experts

MUMBAI: The Bombay High Court on Friday mentioned that an mavens' committee will also be set up to check up on the web site of the hot wall cave in in suburban Wadala and recommend remedial measures.

A department bench of Justices AS Oka and Riyaz Chagla was hearing a petition filed via Dosti Blossom Society, difficult the permission granted to Dosti Realty to build high-rise structures in the area.

Society's lawyer Atul Damle mentioned the construction was causing damage to the existing structures in the area, together with Dosti Blossom.

Referring to the incident on June 25, when compound wall of Lloyd Building adjoining to the construction web site of Dosti Realty collapsed, burying a number of automobiles in particles, he demanded that the realty company must be asked to not carry out additional building.


Dosti Blossom citizens moved the courtroom after Monday's incident.


Lawyer of the Brihanmumbai Municipal Corporation (BMC) Anil Sakhre mentioned a stop-work notice has already been issued to Dosti Realty, and only remedial work of backfill and concretization of the collapsed wall was on.


The courtroom steered that each one parties to the petition can choose an expert institution such as the IIT-Bombay or the city-based Veermata Jijabai Technological Institute (VJTI) to behavior web site inspection.


"The parties can get in touch with expert institutions and let us know tomorrow. We will appoint that institution so that work (on remedial measures) can begin immediately considering the grave nature of the case," Justice Oka mentioned.