Ukkadam flyover to be completed before deadline: Highways dept

Commencing the Ukkadam flyover mission a few year in the past, the state highways division has already finished 50% of the development paintings. It is much more likely to finish the mission much forward of the closing date. Works to put deck (highway layer of the flyover) is expected to commence via subsequent month.
An professional from the state highways division stated, “At present, paintings to put in piles, pile caps and girders for a stretch of one.47km between Ukkadam Junction and Karumbukkadai Junction is happening. We have finished greater than 60% of the paintings.”

The professional stated they'd commence laying deck from subsequent month and the development paintings is expected to be finished at least six months before the closing date. The development paintings of the mission commenced on April 2018 with a closing date of 30 months.

Explaining that the dept is planning to extend the flyover until Aathupalam Junction, the professional stated the dept has been working to get approval for the extension before the of entirety of the existing flyover plan, so that the extension paintings might be carried out without delay.

A 110kv tower line from TANGEDO’s substation at Ukkadam to Sungam Bypass Road is passing in the course of the centre of the street until Periyakulam tank, which could cause inconvenience while setting up the flyover. Superintending engineer of the dept S Suresh stated the electric line could be laid underground.


He stated a separate mushy used to be floated to make the tower line as underground wires and the bidder is but to be finalized. The wires for about 1,000meters could be tucked underneath the ground at the price of Rs nine crore roughly.


While the dept has bought land between three to 16m alongside the Palakkad Main Road and negotiations on finalizing the compensation amount is being carried out, a section of households on corporation land close to Perur Bypass Road is but to be removed, the professional stated.


The professional stated they'd commence the eviction process best after the election and they have already determined to offer alternative accommodation to the households in the course of the Tamil Nadu Slum Clearance Board. Sixty-four households from Dobhikana and about 700 households from corporation employees colony could be removed to finish the mission.