Expect flooded Delhi roads again this monsoon

NEW DELHI: Thursday’s scenes of waterlogged roads and long site visitors jams in rain-hit Mumbai could neatly be enjoying out in Delhi a few weeks later. For, the time limit set for de-silting of drains within the capital is just eight days away and the civic companies are woefully behind schedule.

The scenario is especially worrisome in East Delhi, where the municipal corporation has handiest been able to succeed in barely 20% of the desilting target while 78% (244 out of 312) of the Public Works Department’s drains currently fall underneath the category of “less than 25% de-silting”.

PWD minister Satyendar Jain had introduced in April that de-silting work will probably be over via June 15. However, in 70% of the sites (726 out of one,036), the dep. has not even finished 25% de-silting. Only 87 sites were totally cleared, in keeping with the newest document.

In the East zone, 78% of the drains fall underneath the “less than quarter” category. The corresponding figures in North and South zones are 75% and 49%, respectively.

The standard date of the monsoon’s arrival within the capital is June 29. For the civic companies, it will be a frantic race towards time from here on. In the PWD’s Monday evaluate assembly held via the engineer-in-chief, officers talked concerning the “pressing want to expedite growth”.

A equivalent story had performed out last 12 months. Roads were severely waterlogged in numerous portions of town after gentle rain of Five-10mm. The extend in de-silting had led to a tussle between the government and bureaucracy, with leader minister Arvind Kejriwal in the hunt for action towards then PWD secretary Ashwani Kumar for not obeying his orders on de-silting.

This 12 months, lieutenant governor Anil Baijal had shaped a high-level committee to look after de-silting and opening of manholes within the capital. The committee was anticipated to coordinate with various companies so that they did not finally end up passing the greenback among each and every other.


Among the municipal firms, the placement is the most acute in East DMC areas. A senior DEMS (sanitation division) reputable blamed the protests and legal obstacles in finding a silt dumping website online for the extend.


Dumping of silt on the Ghazipur landfill was banned after last 12 months’s landfill collapse which claimed two lives. We had began depositing silt on the Geeta Colony website online but locals began protesting and the dumping was stayed via courts,” reputable stated.


The reputable claimed that desilting work handiest began prior to now week after the civic frame was given a location at Singhola village near Singhu border (Narela) for dumping. “The new website online is on the double the gap from the previous one. This has made de-silting a lot more expensive for the cash-strapped frame,” he added.


The north corporation has claimed 70% of its desilting work is over and that it might meet the time limit. “We are expediting work at the entire last sites to complete within the next week,” a spokesperson stated. South DMC has claimed that 97% of its allotted work is over. These claims will face the rain check when the monsoon arrives.
Expect flooded Delhi roads again this monsoon Expect flooded Delhi roads again this monsoon Reviewed by Kailash on June 08, 2018 Rating: 5