Longest river ropeway across Brahmaputra set to miss date with Modi

Guwahati: The aerial passenger cable automotive provider connecting north and south Guwahati over the Brahmaputra — which is all set to be the longest ropeway provider across a river within the nation — will pass over its date with Prime Minister Narendra Modi.
Reports were doing the rounds that the Rs 56.08-crore Guwahati Metropolitan Development Authority (GMDA) project can be inaugurated by means of Modi, who arrived right here on Friday, however senior officials of the urban building body mentioned the provider shall be ready for formal opening best by means of April. Trial runs are all set to start out from mid-February, officials added.

“GMDA would have been happy if the Prime Minister could have inaugurated the Guwahati aerial tramway all over his discuss with. But taking into account the ground reality and delays brought about by means of redesigning of the project, Modi-ji could now not be invited to open the aerial tramway,” a senior GMDA reputable told IdealNews on Friday. While set up of equipment on the project web page is at the verge finishing touch, the reputable mentioned that the project is yet to be commissioned.

The 1820-metre-long ropeway has a lower terminal at Panbazar, in entrance of Nehru Park and an upper terminal at Rajadwar village, at the back of the Dolgovinda Temple, with options on offer corresponding to a passenger-handling area, ticket counter, parking facility and public convenience area.

Work at the reversible, zig-back bi-cable ropeway provider was once previous scheduled to be completed by means of January this year, but the project were given not on time due to interruptions along the way in which.


Construction paintings of the project started in 2009 and part of it was once completed by means of February, 2011. But paintings then swiftly came to a halt in 2011 following objections from the Archaeological Survey of India, which mentioned the project posed a danger to Urvashi Island within the Brahmaputra. The basic construction of project was once redesigned and paintings subsequently started again in January, 2017.


GMDA sources mentioned that the first group of professionals from the Garaventa AG, Switzerland, the safety certificate issuance agency, will land in India in mid-February, after which the trial runs shall be performed in their presence. After a minimum of 30 days of trial run, every other group of professionals from the agency is likely to arrive in Guwahati in mid-March for giving the overall go-ahead.


“We predict that the project will develop into operational sooner than the festive season of Rongali Bihu in April,” the reputable mentioned, adding that the the ropeway cable automotive, which could have a capacity of wearing 30 passengers for a unmarried travel, shall be a major level of tourist appeal.