Linking UGD pipelines to STPs to be completed in 8 months

Coimbatore: The town corporation is more likely to whole the linking of sewer lines of underground drainage (UGD) from buildings to the 3 sewage remedy plants (STPs) in 8 months.
“We have laid pipelines in many of the spaces and best the distance paintings for over 10km is pending,” stated a senior reliable from the corporation.

Most of the distance works which might be to be performed are in Trichy Road, between Singanallur and Ondipudur area, the reliable stated, including that they are these days doing the UGD paintings in Singanallur area.

As the Trichy Road is one of the maximum congested roads within the town and the street after Singanallur area turns into slim, the reliable stated that the civic frame would take no less than six to eight months to finish the project.

While the sewer lines had been laid at a median depth of 1 meter within the centre of the town, the depth could be larger because the lines had been laid in opposition to the border limits, the reliable stated.

As the lines could be laid at the depth of 3 meters from Singanallur and difficult stratum (onerous rock) was once discovered at that depth within the area, the reliable stated that they are going to must do control blasting to lay pipelines and they are planning to do throughout the night time hours.


“We have to be very careful while doing control blasting as this can be a residential house or even a small mistake would create a big impact,” the reliable added.


The project that was once introduced below the Jawaharlal Nehru National Urban Renewal Mission (JNNURM) has commenced throughout 2009 and around 9 years later, the civic frame has laid sewer pipelines for 572km across the town.


The project was once being achieved in 3 phases and the sewer lines from the buildings within the town could be attached to 3 sewage remedy plants (STPs) – 70MLD unit at Ukkadam, 40MLD unit at Nanjundapuram and 60MLD unit at Ondipudur.