Mumbai Expressway off to quick start, tenders floated for five sections

NEW DELHI: In a document of sorts, the National Highways Authority of India (NHAI) has floated tenders for five sections of Delhi-Vadodara hall of Mumbai Expressway slightly five months after the plan was once first introduced. The stretch might be a part of the new greenfield throughway that can attach the nationwide capital.

The whole throughway has been divided into 22 sections in order that building paintings can start concurrently for faster execution. Two of the five sections for which tenders had been floated duvet the stretch between the Kundli Manesar Palwal (KMP) throughway intersection close to Sohna and the border of Haryana and Rajasthan. The other three sections fall in Rajasthan and canopy the stretch as much as Dausa.

The five sections duvet about 118 km of the throughway and the construction cost can be about Rs four,600 crore.

While pronouncing the throughway project at a TOI event in April this 12 months, highways minister Nitin Gadkari had mentioned the project might be finished inside of three years. This new highway will cut back the gap between Delhi and Mumbai by means of 200 kilometres and shuttle time by means of 12 hours since it is going to be a sign loose stretch. The highway might be of eight lanes.

Fast monitoring the land acquisition procedure, the NHAI has already issued the primary notification figuring out the land by which the throughway might be built.


"We have already appointed officers for expeditious land acquisition and to complete the preparatory work. We are carrying out strict monitoring of daily progress. Project execution will not be an issue since the entire road will be built with full funding from the government," a freeway ministry legitimate mentioned.


Usually, preparation of detailed project report and fixing alignment take a couple of 12 months after government takes the verdict to extend or construct a new freeway and therefore issuing notifications for acquiring land steadily takes at least one-and-a-half years to two years. Sources mentioned the federal government has fast tracked the process in order that the paintings can start earlier than the dates for Lok Sabha elections are introduced.


The NHAI has set two years as target for building paintings. "We will float tenders for all the 22 sections by end of September," mentioned the legitimate. Since maximum stretches of the throughway will move through backward regions, the NHAI expects no main hurdle in getting the land bearing in mind that the locals would get honest reimbursement for their land.


The highways ministry has decided to go for building new alignment roads with immediately connectivity quite than expanding the prevailing corridors. Expansion of roads passing through already built up spaces is expensive because of top land cost and also as a result of building gets delayed due to problem in getting green clearances and removing of encroachments.
Mumbai Expressway off to quick start, tenders floated for five sections Mumbai Expressway off to quick start, tenders floated for five sections Reviewed by Kailash on August 25, 2018 Rating: 5